BUILDING CONSTRUCTION DETAILS
For any questions or concerns please contact the Office of Campus Planning & Facilities at campus.facilities@lehman.cuny.edu or 718-960-8226.
Shuster Hall Carman Hall Old Gym Campus Bridge Gillet Hall Library Music Building Davis Hall
Carman Hall
Carman Hall Projects
- HVAC Upgrade (Jan '27 - Jan '28)
- This project will require most of Carman Hall to be closed beginning January 2027 for one year. Please read our preliminary information on the closure.
- Read our list of Carman Work FAQs
- Bathroom Accessibility Improvements (January '26 - May '27)
- PLEASE NOTE: Subbasement, some first floor, and some third floor restrooms are now closed for renovation work to improve accessibility through July, 2026.
- Restrooms on the basement and second floor will continue to be open and are accessible by stair and elevator. Additionally, restrooms in CA 102, 106, 314, and 346 will remain open.
- Terraces Rebuild COMPLETE
- East Main Staircase/Entrance Rebuild COMPLETE
- Plaza Roof Replacement COMPLETE
- West Main Staircase/Entrance Rebuild COMPLETE
Carman Hall |
||||||||||
|---|---|---|---|---|---|---|---|---|---|---|
Construction Projects |
||||||||||
| Oct-25 | Nov-25 | Jan-26 | Feb-26 | April-26 | June-26 | Aug-26 | Jan-27 | May-27 | Jan-28 | |
| Plaza Roof | ||||||||||
| West Staircase/Entrance | ||||||||||
| East Staircase/Entrance | ||||||||||
| Terraces | ||||||||||
| Bathrooms | ||||||||||
| HVAC | ||||||||||
Shuster Hall
Window Replacement (Estimated Construction Time)
UPDATE: Shuster Hall window replacement is back on track with several offices in the basement and first floor being moved.
- Admissions is now in the former Book Store.
- Enrollment Management is now in Shuster 279.
- Onboard Advising is now in Old Gym 308B.
- Print Shop beginning the week of October 5, will be accessible from Shuster 050.
- Parking Permits are now in Shuster 034.
- IDs are available in the Old Gym B003B.
The following offices remain in their temporary locations:
- Strategic Planning, Assessment, and Institutional Research (SPAIR) is in 359.
- Campus Planning and Facilities is in T3 Building, Rooms 219, 221A, and 221B.
- Institutional Advancement - T-3 Building, Room 209
- Research Administration, Compliance, Learning, and Enhancement (ORACLE) remains remote.
Shuster Hall |
|||||
|---|---|---|---|---|---|
Window Replacement |
|||||
| Oct-25 | Aug-26 | Sept-26 | Oct-26 | Nov-26 | Dec-26 |
| Third Floor | |||||
| Basement | |||||
| Second Floor | |||||
| First Floor | |||||
HVAC (Air Conditioning) Replacement (Estimated Construction Time)
UPDATE: You may have noticed the ceilings are now exposed in Shuster. This is part of a new Phase Zero, that includes removal of the existing ceilings to permit accurate surveys to be made of the existing conditions. These surveys are necessary to create precise drawings that will be used to construct the new ductwork that will begin to be installed later this calendar year in the fall.
- Basement & First Floor – North and West Corridors (10/1/26 – 3/1/27)
- Second & Third Floor – North and West Corridors (4/1/27 – 10/1/27)
- Basement & First Floor – South and East Corridors (11/1/27 – 3/1/28)
- Second & Third Floor – South and East Corridors (1/1/28 – 9/1/28)
Shuster Hall |
|||||||
|---|---|---|---|---|---|---|---|
HVAC Upgrades |
|||||||
| Oct-26 | Mar-27 | Apr-27 | Oct-27 | Nov-27 | Jan-28 | Mar-28 | Sept-28 |
| Basement/First Floor - North & West Corridors | |||||||
| Second/Third Floor - North & West Corridors |
|||||||
| Basement/First Floor - South & East Corridors |
|||||||
| Second & Third Floors - South & East Corridors |
|||||||
Old Gym Building
Center for Teaching and Learning (Estimated Construction Time)
(Completed by September '26)
Window Replacement (Estimated Construction Time)
This project has not been put out to bid yet.
Old Gym Building |
|||
|---|---|---|---|
Construction Projects |
|||
| Oct-25 | Feb-26 | Oct-26 | Aug-28 |
| Center for Teaching & Learning | |||
| Window Replacement - TBD | |||
Campus Bridge
Structural Restoration (Estimated Construction Time)
(Jan '26 – Winter '26)
Campus Bridge |
||
|---|---|---|
Structural Restoration |
||
| Jan-26 | June-26 | Dec-26 |
| Repair and Restoration | ||
Please Note: The walkway under the Campus Bridge is now the accessible route to enter the lower level of the Library. The lower level exit of the Music Building facing the bridge remains closed until further notice.
Leonard Lief Library
PROJECT COMPLETED
Window Replacement (Estimated Construction Time)
- Third Floor (1/26 – 4/26)
- Second Floor (4/26 – 5/26)
- First Floor (5/14/26 – 7/25/26)
- Basement (5/14/26 – 7/25/26)
Leonard Lief Library |
|||
|---|---|---|---|
Window Replacement |
|||
| Jan-26 | Apr-26 | May-26 | July-26 |
| Third Floor | |||
| Second Floor | |||
| First Floor | |||
| Basement | |||
Music Building
Projects Completed
Facade Work / Copper Roof Refurbishment (Estimated Construction Time)
(7/5/25 – 8/1/26)
Music Building |
||
|---|---|---|
Facade and Roof Repair |
||
| Oct-25 | Jan-26 | August-26 |
| Facade Work | ||
| Copper Roof Refurbishment | ||
Davis Hall
PROJECTS COMPLETED
Roof Replacement (Estimated Construction Time)
(7/5/25 – 8/1/26)
Social Work (April '26)
Davis Hall |
||
|---|---|---|
Construction Projects |
||
| Jun-25 | Dec-25 | Jan-26 |
| Roof Replacement | ||
| Social Work Department | ||
Gillet Hall
PROJECT COMPLETED
Roof Replacement (Estimated Construction Time)
(9/5/25 – 12/20/25)
Gillet Hall |
||
|---|---|---|
Roof Replacement |
||
| Oct-25 | Nov-25 | Dec-25 |
| Roof Replacement | ||
-