BUILDING CONSTRUCTION DETAILS


For any questions or concerns please contact the Office of Campus Planning & Facilities at campus.facilities@lehman.cuny.edu or 718-960-8226.

Shuster Hall Carman Hall Old Gym Campus Bridge Gillet Hall Library Music Building Davis Hall


Carman Hall

Carman Hall Projects
  • Bathroom Accessibility Improvements (January '26 - May '27)
    • PLEASE NOTE: Subbasement, some first floor, and some third floor restrooms are now closed for renovation work to improve accessibility through July, 2026.
    • Restrooms on the basement and second floor will continue to be open and are accessible by stair and elevator. Additionally, restrooms in CA 102, 106, 314, and 346 will remain open.
  • Terraces Rebuild COMPLETE
  • East Main Staircase/Entrance Rebuild COMPLETE
  • Plaza Roof Replacement COMPLETE
  • West Main Staircase/Entrance Rebuild COMPLETE

Carman Hall

Construction Projects
Oct-25 Nov-25 Jan-26 Feb-26 April-26 June-26 Aug-26 Jan-27 May-27 Jan-28
Plaza Roof          
West Staircase/Entrance          
        East Staircase/Entrance    
  Terraces      
    Bathrooms  
              HVAC

Shuster Hall

Window Replacement (Estimated Construction Time)

UPDATE: Shuster Hall window replacement is back on track with several offices in the basement and first floor being moved.

  • Admissions is now in the former Book Store.
  • Enrollment Management is now in Shuster 279.
  • Onboard Advising is now in Old Gym 308B.
  • Print Shop beginning the week of October 5, will be accessible from Shuster 050.
  • Parking Permits are now in Shuster 034.
  • IDs are available in the Old Gym B003B.

The following offices remain in their temporary locations:

  • Strategic Planning, Assessment, and Institutional Research (SPAIR) is in 359.
  • Campus Planning and Facilities is in T3 Building, Rooms 219, 221A, and 221B.
  • Institutional Advancement - T-3 Building, Room 209
  • Research Administration, Compliance, Learning, and Enhancement (ORACLE) remains remote.

Shuster Hall

Window Replacement
Oct-25 Aug-26 Sept-26 Oct-26 Nov-26 Dec-26
Third Floor  
    Basement  
        Second Floor
        First Floor

HVAC (Air Conditioning) Replacement (Estimated Construction Time)

UPDATE: You may have noticed the ceilings are now exposed in Shuster. This is part of a new Phase Zero, that includes removal of the existing ceilings to permit accurate surveys to be made of the existing conditions. These surveys are necessary to create precise drawings that will be used to construct the new ductwork that will begin to be installed later this calendar year in the fall.

  • Basement & First Floor – North and West Corridors (10/1/26 – 3/1/27)
  • Second & Third Floor – North and West Corridors (4/1/27 – 10/1/27)
  • Basement & First Floor – South and East Corridors (11/1/27 – 3/1/28)
  • Second & Third Floor – South and East Corridors (1/1/28 – 9/1/28)

Shuster Hall

HVAC Upgrades
Oct-26 Mar-27 Apr-27 Oct-27 Nov-27 Jan-28 Mar-28 Sept-28
Basement/First Floor - North & West Corridors            
    Second/Third Floor -
North & West Corridors
       
        Basement/First Floor -
South & East Corridors
 
          Second & Third Floors -
South & East Corridors

Old Gym Building

Center for Teaching and Learning (Estimated Construction Time)

(Completed by September '26)

Window Replacement (Estimated Construction Time)

This project has not been put out to bid yet.

Old Gym Building

Construction Projects
Oct-25 Feb-26 Oct-26 Aug-28
Center for Teaching & Learning
    Window Replacement - TBD

Campus Bridge

Structural Restoration (Estimated Construction Time)

(Jan '26 – Winter '26)

Campus Bridge

Structural Restoration
Jan-26 June-26 Dec-26
Repair and Restoration

Please Note: The walkway under the Campus Bridge is now the accessible route to enter the lower level of the Library. The lower level exit of the Music Building facing the bridge remains closed until further notice.


Leonard Lief Library

PROJECT COMPLETED

Window Replacement (Estimated Construction Time)
  • Third Floor (1/26 – 4/26)
  • Second Floor (4/26 – 5/26)
  • First Floor (5/14/26 – 7/25/26)
  • Basement (5/14/26 – 7/25/26)

Leonard Lief Library

Window Replacement
Jan-26 Apr-26 May-26 July-26
Third Floor    
  Second Floor  
    First Floor
    Basement

Music Building

Projects Completed
Facade Work / Copper Roof Refurbishment (Estimated Construction Time)

(7/5/25 – 8/1/26)

Music Building

Facade and Roof Repair
Oct-25 Jan-26 August-26
Facade Work
Copper Roof Refurbishment

Davis Hall

PROJECTS COMPLETED

Roof Replacement (Estimated Construction Time)

(7/5/25 – 8/1/26)

Social Work (April '26)

Davis Hall

Construction Projects
Jun-25 Dec-25 Jan-26
Roof Replacement
Social Work Department

Gillet Hall

PROJECT COMPLETED

Roof Replacement (Estimated Construction Time)

(9/5/25 – 12/20/25)

 

Gillet Hall

Roof Replacement
Oct-25 Nov-25 Dec-25
Roof Replacement